Time Synchronization

Application of Precision Time Protocol Standard with multi-vendor Relays over PRP and HSR Architectures: A Real Test of the PTP Standard in project FITNESS

by P. Mohapatra, SP Energy Networks, UK, C. Popescu, ABB, UK, P. Balasubramani, GE, UK, M. Wehinger and Ali Abdulla, OMICRON electronics

The project called FITNESS (Future Intelligent Transmission Network Substation) is set to be the first multi-vendor digital substation and automation system in the UK led by Scottish transmission network owner SP Energy Networks. It encompasses two circuits covering protection, control and monitoring of the local substation as well as protection at the remote end. More

Let?s start with organization in protection testing