Author: Clare Duffy, ESBI, Ireland
The Union for the Coordination of Transmission of Electricity (UCTE) grid suffered a severe disturbance on 4 November 2006. Immediate action by TSOs prevented a Europe-wide blackout. This article summarizes the findings (http://www.ucte.org) from the subsequent UCTE investigation.
E.ON Netz was requested to disconnect the double circuit 380kV line Diele-Conneforde in Northern Germany on 5 November at 01:00. E.ON Netz's empirical analysis showed no violation of the N-1 (The N-1 security rule aims at avoiding cascading effects and requires that a single incident should not jeopardize the secure operation of the interconnected network) criterion from the proposed switching in its network. On the 27 October E.ON Netz provisionally approved the switching request and informed neighboring TenneT and RWE TSO. Results of their N-1 analysis confirmed that the grid would be highly loaded but secure.
The manual switching of the Diele-Conneforde line on the 4 November caused increased power flow on the Landesbergen-Wehrendorf line (interconnection between E.ON Netz and RWE TSO). Action taken to remedy the situation actually deteriorated line loading eventually causing it to trip. This triggered cascade tripping splitting the UCTE synchronously interconnected grid (which covers 23 countries across Europe) into 3 islands (West, North East and South East - see figure 1) causing significant power imbalances in each island. Initial power imbalances in the West induced a severe frequency drop interrupting power supply to more than 15 million West European households. Sufficient generation reserves in the under-frequency areas (West and South East) allowed restoration of normal frequency in a relatively short time.
Lack of control over generation units (quick reduction of schedules and automatic reconnection of wind generation) in the over-frequency area (North East) contributed to a deterioration of system conditions in this area (long lasting over-frequency and severe transmission line overloading) and complicated the process of restoring normal system conditions.
Full resynchronization of the 3 islands was completed 38 minutes after the system split and normal conditions were restored in all European countries in less than 2 hours.
Evolution of system conditions before system splitting
21:29 | E.ON Netz load flow calculation and N-1 empirical evaluation did not indicate any violation of limit values for the 380kV double circuit Diele-Conneforde line switching. |
21:30 | RWE TSO's load flow calculation and N-1 analysis confirmed that the grid would be highly loaded but secure. |
21:38 | E.ON Netz switched off first circuit of the 380kV Diele-Conneforde line. |
21:39 | E.ON Netz switched off second circuit of the 380kV Diele-Conneforde line. |
21:39 | E.ON Netz received warning messages about high power flow on the Elsen-Twistetal and Elsen-Bechterdissen lines. |
21:41 | Switching of the Diele-Conneforde line resulted in a significant increase (600MW) in the power flow on the 380kV Landesbergen-Wehrendorf line (interconnection between E.ON Netz and RWE TSO). RWE TSO informed E.ON Netz about the safety limit of 1,795A on this line although current was still below the limit and the N-1 criterion was being met in the RWE TSO network at that time. |
Protection settings on both sides of the Landesergen-Wehrendorf line are different (see Table 1). Despite previous settings data exchange among TSOs, E.ON Netz claimed they were unaware of the differences and did not take the actual Wehrendorf (RWE TSO substation) values into account.
E.ON Netz (Landesbergen) | RWE TSO (Wehrendorf) | |
Steady state value (thermal | 2000A | 2000A |
Warning value (alarm) | 1000A and 2000A | 1795A (90% of maximum limit value) |
Maximum accepted value | 2 550 A (85% of tripping current) for a maximum time 1 hour | 1995 A (95% of the tripping current) |
Tripping current | 3000A | 2100A |
Table 1: Current limit values on the line Landesbergen-Wehrendorf
21:46, 21:50 and 21:52 | Telephone calls between E.ON Netz, RWE TSO and Vattenfall Europe noting tight situation. |
Between 22:05 and 22:07 | Load on the 380kV Landesbergen-Wehrendorf line exceeded RWE TSO's alarm level of 1,795A |
22:08 | RWE TSO requested E.ON Netz to intervene to restore safe grid operation. |
E.ON Netz's empirical assessment of corrective switching measures suggested that coupling the busbars in Landesbergen substation would reduce current. They initiated this switching at 22:10 without coordination with RWE TSO. Contrary to expectations the line current increased. Wehrendorf substation (RWE TSO) protection tripped and triggered cascade tripping all over the UCTE area.
UCTE Separation
The UCTE system split into 3 areas at 22:10:28. The interconnection between Morocco and Spain tripped on low frequency at 22:10:32. Figure 2 shows the frequency in the 3 areas from 22:10:06 to 22:10:30. Time stamps of key events are indicated.

Figure 3 shows the frequency for the 3 islands from 22:09:30 to 22:20:00 are shown. The split caused a power imbalance by cutting 9,500MW power transfer from the East to the Western area which induced a frequency drop to 49Hz in the West. The corresponding power surplus in the North East increased the frequency to 51.4Hz. The split caused an 800MW power deficit in the South East area inducing under-frequency of 49.7Hz.
Resynchronization
A number of resynchronization attempts took place however the first successful reconnection between the West and North-East areas was completed at 22:47:11 on the 380kV Bechterdissen-Elsen line. The frequency and phase angle differences prior to connection were 180mHz and less than 10.
The first successful reconnection between the already reconnected West and North-East areas and the South-East was at 22:49. The resynchronization was completed when the last 400kV line between Croatia and Hungary was switched in at 23:57.
Analysis indicates 2 root causes and 6 critical factors.
Root Causes
E.ON Netz coupled the busbars in the Landesbergen substation in an effort to reduce the loading on the Landesbergen-Wehrendorf line. This was done without numerical analysis of the impact of this change on the power flow. The result was contrary to E.ON Netz's empirical assessment. It caused the line to trip triggering the cascade tripping that split the grid.
Prior to the triggering event at the Landesbergen substation E.ON Netz did not fully coordinated with TSOs. No account was taken of different protection settings on either side of the Landesbergen-Wehrendorf line (i.e. on E.ON Netz and RWE TSO systems).
Critical Factors